OCTYS CBTC Project

Transcription

OCTYS CBTC Project
OCTYS CBTC Project
Département ING/STF (Transport System Unit of the Engineering division) of RATP
Open Control of Train Interchangeable & Integrated System
Nicolas ESTIVALS
OCTYS CBTC project
2
Contents
1. Overview of the Paris network, CBTC projects
2. Modernization Program for Metro
3. Interchangeability - concepts and strategy
4. Schedules & migration
5. Key challenges & lessons learnt
STF, 2011/12/01
1
OCTYS CBTC project : context
RATP, a national public service company
3
State-owned national company created in
1949 as a public service company
One of the worldwide largest public
transport network:
RER (Suburban)
2 lines (A & B)
115 KMs (double tracks)
67 Stations
357 Trains
446 million travels/year
Metro
Bus & Tramway
351 Bus routes
14+2 lines (1 to 14)
+ 3 Tramway lines
202 KMs (double tracks)
3 868 KMs
300 Stations
7 816 Stations
689 Trains
4 300 Buses + 82 Trams
1 388 million travels/year
1 031 million travels/year
STF, 2011/12/01
OCTYS CBTC project : context
CBTC Projects on existing lines
All figures 2008
4
UTO
• SAET L14 (Siemens)
Energy consumption optimized
(implemented since may 2011)
Increase of throughput adding 4 trains
(Æ end 2012)
• SAET L1 (Siemens)
On revenue service since November 3rd
Æ Gradual injection of UTO trains
Æ Great Success !
STO
• OURAGAN on line 13 (Thalès)
• OCTYS on lines 3, 5, 9 (this presentation)
STF, 2011/12/01
2
OCTYS CBTC project : context
Objectives for the Modernization/ OCTYS contribution
5
Obsolescence reduction
Replacement of older systems, tricky to maintain ÖOCTYS : new ATP/ATO
+ Renewal of Signalling system
(components & knowledge obsolescence)
Safety improvement
Compliance with new safety standards (CENELEC) Ö OCTYS : ATP
Continuous speed control (incl. in manual driving mode) Ö OCTYS : ATP
Passengers capacity increase
Headway, Regulation, Trains diagrams
Ö OCTYS : ATP (type 1) + ATO
Quality of service increase
Ö OCTYS : Full redundancy ATP/ATO
Availability & maintainability of new systems + Maintenance Support System (BITE …)
Performance of degraded modes management
Passenger exchange control (Platforms screen doors) Ö OCTYS : Ability to be
interfaced
Operation Costs reduction
Reduction of staff in terminus (centralized OCC)
Less staff for line operation (when in driverless mode)
Ö OCTYS :ATO
Less trains (thanks to commercial speed improvement)
Energy savings (with dedicated driving profiles in ATO mode) Ö OCTYS :ATO
STF, 2011/12/01
OCTYS CBTC project : context
Network modernization Master Schedule
6
RATP current CBTC Projects
UTO existing
(SAET L14)
UTO on progress
(SAET L1)
STO on progress
(OUR L13)
STO on progress
(OCTYS L3, 5 & 9)
STO contracted
(OCTYS L10 & 12)
CBTC projected
(all other M° lines)
STF, 2011/12/01
3
OCTYS CBTC project
7
Zoom on lines 3, 5 and 9
Bobigny -Pablo
Picasso
Pont de Levallois
Bécon
Gare du Nord
3
Porte des
Lilas
Km
11.7
Stations
25
Trains
45 MF67
Headw ay
110s
3b
République
TCC - Saint-Fargeau
Gallieni
Mairie
Montreuil
Gambetta
9
5
TCC - Voltaire
TCC - Bastille
Km
19,5
Stations
37
Trains
66 MF01
Headw ay
105s => 90s
Km
14.6
Stations
22
Trains
Headw ay
51 MF2000 105s => 90s
Place d’Italie
Pont de
Sèv res
STF, 2011/12/01
OCTYS CBTC project : Interchangeability
Concept of Interchangeability
•
8
Ensure competitive procurement of interoperable
CBTC/OCTYS systems for:
ƒ other lines
ƒ line extensions
ƒ rolling stock retrofit or renewal
ƒ upgrade of obsolescent pieces of equipment
ƒ equipment evolutions
•
Establish design and operational standards for
CBTC/OCTYS implemented by RATP
STF, 2011/12/01
4
OCTYS CBTC project : Interchangeability
Concept of Interchangeability
9
OCTYS is a program for renewal of Train Control Systems (CBTC):
based on the Interchangeability Concept applied to CBTC systems
for metro lines to be renewed in STO mode
OCTYS = Open Control of Trains, Interchangeable & Integrated System
i.e.: Interchangeable CBTC
OCTYS Contract signed in 2004 with 3 suppliers (ANSALDO, AREVA &
SIEMENS), for 5 lines to be revamped, in parallel with:
OCC modernization program
Rolling stock retrofit or renewal program
Signalling and Interlocking modernization program
STF, 2011/12/01
OCTYS CBTC project
10
Technical features
A generic system :
z Features :
z
Reduced headway
Optional equipments
Cab-signal
Simplified wayside signalling
Wayside signalling cancellation
Train Detection reliability
Platform Screen Doors
Guideway Intrusion Detection
Full redundancy
) Driving modes
ATO mode
Manual mode (full train
protection)
Automated Turnback Mode
Civil Speed Protection Mode
)
)
)
LIGNE 3
no (110s)
z LIGNE 5 , 9
)
reduction by 15%
…
;
…
…
;
;
;
…
;
;
…
…
;
;
;
;
…
;
;
;
;
;
new RS
ability
ability
STF, 2011/12/01
5
OCTYS CBTC project: Interchangeability
General standardized CBTC architecture
11
Interchangeable CBTC “OCTYS”
Trainborne ATC
Data Transm ission
System
Beacons
Computerized
Interlocking
Rolling Stock
Trainborne Radio
Trackside Radio
and Backbone
Block Relay
Signalling
Fixed ATC
OCC
PSD
Contract Share
(Interchangeable component)
Standardized Interface
STF, 2011/12/01
OCTYS CBTC project : Procurement
Contract sharing for CBTC system
Lines 3, 12 & 10
12
Lines 5 & 9
Trainborne ATC
Trainborne ATC
Trainborne Radio
SIEMENS
AREVA
Trackside Radio
and Backbone
Fixed ATC
Data Transm ission
System
Data Transm ission
System
ANSALDO
Trainborne Radio
Trackside Radio
and Backbone
Fixed ATC
STF, 2011/12/01
6
OCTYS CBTC project : Design documentation
Interchangeability Baseline documentation
Interlocking,
power supply,
platform
equipments
Zone
controller
(Section A)
OCC
I/O
Interface
E2
Zone
controller
(Section B)
E1
I1
I2
I2
Data Communication System (LAN + Radio)
I5
Functionally independent
Modem radio
Cab-signal
O&M:
SAM , ED …
External Interfaces
E1 Between OCTYS and TCC
E2 Between OCTYS and auxiliary (Interlocking, etc.)
E3 Between OCTYS and Rolling Stock
E4 Between OCTYS and Location System
I3
On-board
Equipment
13
E4
SLB
I4
Rolling
Stock
E3
Internal Interfaces
I1 Between DCS and I/O Interface module
I2 Between DCS and Zone controller
I3 Between DCS and On-Board equipment
I4 Between On-Board equipment and cab-signal
I5 Between DCS and Operation & M aintenance system
STF, 2011/12/01
OCTYS CBTC project
BAQUS Validation Test bench “hardware-in-theloop”
14
« Target » real equipments
from different suppliers
System Qualification Tests Bench
Functional
Model
PAE
On board
Equipement
HMI
Tests
Scénario
Simulateur
Environment
simulator
(Functional
models:
Interlockings,
Wayside
signalling,
switchs, TCC
Trains
Driver…)
Supplier A
Supplier B
Supplier C
Functional
Model
PAS
Functional
Model
MES
Functional
Model
FRONTAM
Data
communication
system emulator
Zone controller
Equipment
Inputs /outputs
Module
Traffic Control
Center server
STF, 2011/12/01
7
OCTYS CBTC project
L3 & L5 schedule
15
Interchangeability
tests
focused on L3
Summer 2009
Line 3 :
OCTYS
intermediate
phase (VB1)
March 2010
Interchangeability
standard
April 2007
OCTYS
Contract
March 2004
Line 5
OCTYS
Revenue
Service (VB2)
End of 2013
Line 3 OCTYS
Revenue
Service (VB2)
January 2012
Line 5 : OCTYS
intermediate phase (VB1)
2nd half of 2012
Mixed fleet op.
18months
2004
2005
2004
2006
2005
20072006 2008 20072009
2008
2010
2009
2011
2012
2013
MF67 -MF2000 Mixed operation
From beginning of 2011
End of L5
signaling
Beginning
2012
End of L3
signaling
September
2009
Signaling contracts
March 2004 - Nov. 2005
TCC Line 3
Revenue Service
September 2009
Testing track
May 2005
L5 : Light
Version For
MF01
June 2011
TCC Line 5
Revenue Service
mid-2012
STF, 2011/12/01
OCTYS CBTC project
L9 schedule
OCTYS L9
Optional Share
April 2011
2011
16
Line 9
OCTYS
Revenue
Service (VB2)
November
2018
Line 9 : OCTYS
intermediate phase (VB1)
January 2015
2012
2004
2013
2005
20142006 2015 20072016
2008
2017
2009
2018
2019
2020
MF67 -MF2000 Mixed operation
From mid-2013
End of Phase 1
End of L9
signaling
Phase 2
signaling
contracts
Mid 2014
April 2018
Signaling contracts
phase 1
September 2011
L9 : Light
Version For
MF01
September 2013
STF, 2011/12/01
Phase 2
TCC Line 9
Revenue Service
Mid 2018
8
OCTYS CBTC project
Migration strategy
17
Current situation
Trains operated in block mode with ATP/ATO
(Speed Code ATC using magnetic loops)
Line operated from centralized OCC + Terminus
Term inus
Relay
Interlocking
Former Autom atic Train Control (ATC)
Speed Code Magnetic Loops
Line Relay
Interlocking
Term inus Control Room
STF, 2011/12/01
OCTYS CBTC project
Migration strategy
18
Step 1: renewal of signals (LED) and interlocking
new interlocking functions under a night/day switch
installation of beacons, optical barriers & radio AP
Renewed
Computerized Interlocking
Beacon
Line Relay
Interlocking
STF, 2011/12/01
9
OCTYS CBTC project
Migration strategy
19
Step 2: CBTC Installation & tests at night,
OCC renewal
Radio
Access
Point
Backbone data network
Zone
& Line
Controllers
Line
rem ote I/Os
Line Relay
Interlocking
Renewed OCC
STF, 2011/12/01
OCTYS CBTC project
Migration strategy
20
Step 3: first train in revenue service in CBTC mode
mixed train operation: block mode performances
Drivers training using a “train simulator”
Zone
& Line
Controllers
Line Relay
Interlocking
STF, 2011/12/01
10
OCTYS CBTC project
Migration strategy
Step 4:
21
Signals simplification and cancellation active
Removal of former ATC magnetic loops
All trains in revenue service in CBTC mode
Running in full performance mode
Zone
& Line
Controllers
Line Relay
Interlocking
STF, 2011/12/01
OCTYS CBTC project
Key challenges & lessons learnt
22
Key Challenge
To maintain good level of line availability
No service disruption during migration
Reliability of the new system since the start of the revenue service
Figures achieved
Line 3: CBTC OCTYS type 2 (w/o line capacity increase)
650 nights for system testing & commissioning (late arrival of a “system test bench”)
No service interruption
1 year to achieve an equivalent level of availability compared with legacy ATC
Lessons learnt
Test tracks, system test benches, and “shadow mode testing” are of utmost benefit
Possibility of long time tests without passengers on site to be valuable for availability (done
on UTO line 1)
STF, 2011/12/01
11
OCTYS CBTC project
Key challenges & lessons learnt
23
Key Challenge
Synchronize System migration with Signalling renewal and Rolling Stock replacement
Figures achieved
Line 3: CBTC OCTYS type 2 (w/o line capacity increase)
Signalling renewal late in terminus, leading to a “CBTC service limited to main
section of tracks: excluding of terminus” for 1 year.
Line 5: CBTC OCTYS type 1 (with line capacity increase)
Signalling works complexity not enough anticipated led to postpone system
deployment
=> New trains arriving, operated manually but needing to install a “simplified
trainborne equipment”.
Lessons learnt
Unlock signalling renewal program with CBTC installation (done for the coming next L9)
Anticipate system “minimum requirements” for operation of new trains before complete
CBTC deployment:
Allow for progressive migration strategies
Envisage “standalone” mode of operation for trainborne equipment
STF, 2011/12/01
OCTYS CBTC project
Key challenges & lessons learnt
24
Key Challenge
Minimize costs for CBTC
Figures achieved
CBTC OCTYS (L3, 5, 9, 10 & 12)
Open competition for 5 lines with a single specification,
contracted with 3 suppliers (interchangeability basis)
5 lines contracted for 100 M€2004 (CBTC only, excl. of ATS and
Signalling)
Lessons learnt
Standardize specifications as far as possible
Group (when possible) several lines in a single contract
Keep competition opened with several suppliers: interchangeability
STF, 2011/12/01
12
OCTYS CBTC project
Key challenges & lessons learnt
25
Key Challenge
Minimize impact on operating rules
Figures achieved
CBTC w/o line capacity increase (fixed block mode: OCTYS type 2 on L3 )
Stricly same op. rules but a great number of incidents linked to ergonomics factors.
As for ex:
Zero speed detection needs a delay (~1”) for the CBTC
: but drivers didn't use to wait that much before changing the master mode selector for
turn-back operation => EB applied
With CBTC, the minimum safety distance for approaching a stabled train is about 8m. This may
be reduced with a speed limit at 7 KPH: many drivers are tripped with this limit.
CBTC with Cab-Signal (OCTYS type 1 on L5)
Special care to be brought on the Cab-Signal ergonomics. This ergonomic constraint might
reduce some performances of the system (SACEM experience)
Lessons learnt
Consider ergonomics factors: a digital system actually does not react same as analog ones.
Extensive use of training simulators is of utmost benefit for smooth migration.
STF, 2011/12/01
OCTYS CBTC project
26
Thank you for your attention
STF, 2011/12/01
13