VULLIETY Jean-Paul - Athens presentation_CISG notice
Transcription
VULLIETY Jean-Paul - Athens presentation_CISG notice
Case name & no Goods involved 2014 Germany, 03.07.2014 Saplings/ Cuttings OLG Brandenburg, 5 U (Stecklinge) 1/13 Delay between discovery Holding (Reasonable or not) of defect/ delivery of goods and notification of the defect Delivery of goods Winter 2008/2009 notification of defect 30 April 2009. The court held that the usual reasonable time period for notifying the lack of conformity can last up to 1 month. But in this case, since it was possible to discover the defect from the beginning, the reasonable time period has to be much shorter than usually. In these situations the reasonable time period cannot be longer than 2 weeks. This shorten time period seems to be coherent with the jurisprudence of the Austrian Supreme Court. An die Feststellung der Vertragswidrigkeit oder den Ablauf der Untersuchungsfrist schließt sich eine mit regelmäßig maximal einem Monat bemessene Anzeigefrist nach Art. UNKAUFRUE Artikel 39 Abs. UNKAUFRUE Artikel 39 Absatz 1 CISG an (vgl. Gruber, a. a. O., Art. 39 CISG Rn. 34 m. w. Nachw.), die hier jedoch deutlich kürzer anzusetzen ist, da der Beklagte ja bereits bei einer ersten Sichtung feststellen konnte, dass mindestens 70% der Ruten mängelbehaftet waren. Im Streitfall wird der auf Untersuchungsund Anzeigefrist entfallende Zeitraum daher insgesamt mit nicht mehr als zwei Wochen zu veranschlagen sein, was auch der Rechtsprechung des Obersten Gerichtshofs in Österreich entspricht (vgl. Gruber, a. a. O., Art. 39 CISG Rn. 34 m. w. Nachw.). 2013 France, 21 March 2013 Amphibious Appellate Court excavator Limoges 10/00477 Goods delivered The court did not consider the question of whether the delay was December 2005 reasonable or not. It only stated that the end term of the delay is not the introduction of an action before the courts but the notice of nonNotice of defect sent conformity given by the buyer. The buyer’s action was therefore not yet 25/26 October 2006 by precluded by the statute of limitation. email 1 Case name & no Germany, 3 June 2013 Appellate Court Koblenz (case) 2 U 50/12 Goods involved Ice-cream Two types of “Grundstoffe zur Speiseeisherstellung ”, i.e. base ingredients/material s for the production of ice-cream Switzerland, 26 March Orange/Grapefruit/L 2013 Bundesgericht emon juice and (Organic juices and Orange /Lemon oil organic oil case) 4A_617/2012 France, 13 February Bags 2013 [Supreme Court] 10-24850 Delay between discovery Holding (Reasonable or not) of defect/ delivery of goods and notification of the defect (Mais attendu cependant que ce n’est pas l’action en justice qui constitue Action introduced le terme du délai, mais la dénonciation du vice, que cette dénonciation est before the courts on 6 intervenue régulièrement par un courriel du 25 octobre 2006 puis un second March 2009 du 26 avec une réponse de Bigfloat Oy du même jour, soit dans les deux ans ;) No specific indication. But notification of lack of conformity was made prior to the invoice on which the dispute is based No direct discussion, but implicitly the court held the time period to be reasonable No specific indication In referring to the decision of the first instance, the court explicitly states that the time limit for notification is of six weeks. Not specified The time period of 2 years stipulated at article 39 of the Vienna Convention is a delay for notification of the default and not a delay within which an action must be introduced. Questions concerning the limitation period are not governed by the Vienna Convention but by national laws (…) le délai de deux ans de l’article 39 de la Convention de Vienne est un délai de dénonciation du défaut de conformité et non un délai pour agir ; que la 2 Case name & no Goods involved 2012 France, 27 November Machine 2012 Supreme Court manufacturing 11-24358 staves France, 18 October Christmas trees 2012, Appellate Court Lyon Delay between discovery Holding (Reasonable or not) of defect/ delivery of goods and notification of the defect prescription des actions en justice issues de la vente ne relève pas de la Convention de Vienne du 11 avril 1980, mais des règles nationales telles qu’elles résultent de la Convention de La Haye du 15 juin 1955 sur la loi applicable aux ventes d’objets mobiliers corporels Delivery and notification Il apparaît certes que la recevabilité de son action au regard des of non-conformity on dispositions de l’article 39 de la Convention de Vienne ne peut être the same day 5 May 200 contestée dès lors que le délai de deux ans instauré par ce texte constitue un délai de dénonciation et non de forclusion et que non seulement elle a dénoncé les défauts de conformité au vendeur dès le jour de la réception de la machine soit le 5 mai 2000, mais que bien plus elle a assigné celui-ci devant le juge du fond le 11 décembre 2001. Discovery of defects : le The court held that the delay of 2 months was NOT reasonable. The 12 December 2005 up notification must intervene within a few days or a few weeks, but not in to Christmas months. 11/01896 Notification of defects : Le délai raisonnable pour des marchandises périssables et amenées à être 23 février 2006, i.e. 2 vendues sur la période restreinte des fêtes de Noël peut s’étendre sur quelques jours voire quelques semaines, mais en aucun cas sur deux mois, ce months délai ne permettant pas au vendeur de procéder à ses propres constatations. Germany, 26 Clay September 2012, Supreme Court Discovery of the defects: Between [Buyer] did not lose the right to rely on a lack of conformity of the goods under Art. 39 CISG because they did not give notice to [Seller] specifying 3 Case name & no Goods involved VIII ZR 100/11 Delay between discovery of defect/ delivery of goods and notification of the defect Autumn 2004 and November 2004 (examination conducted in the beginning of November 2004 of the clay on Buyer's premises) Holding (Reasonable or not) Contractually fixed at 48 hours (because it concerns perishable goods) The court did not have to rule on the reasonableness of the delay of notification but on the reasonableness of the seller claiming that the delay started to run from the loading of the goods instead of the discovery of the defect. the nature of the lack of conformity within a reasonable time after they discovered it or ought to have discovered it. This question may be left open because, in any case, [Seller], pursuant to Art. 40 CISG, is not entitled to rely thereon because the dioxin contamination of the delivered clay and the consequential additional necessity to clean the separated potatoes, which limits the fitness for the ordinary purpose of the potato separation clay under Art. 32(2)(a) CISG, are Buyer notified seller on facts of which [Seller] could not have been unaware and which it did not 4 November 2004 disclose to [Buyer]. France, 24 May 2012 Citrus fruits Appellate Court d’Aixen-Provence 10/20457 Attendu que le fait que les marchandises aient été négociées en prix FOT au départ de Poeldjick (Rotterdam) et d'Aubagne a une incidence sur le transfert des risques en ce qui concerne le contrat de transport, mais n'en a aucune sur le contrat de vente sur lequel porte le litige ; que dès lors, la société C... n'est pas fondée à prétendre que le délai raisonnable de contestation, que les parties dans leurs conclusions s'accordent à fixer à 48 heures, s'agissant de denrées périssables, ait commencé à courir à compter du chargement de la marchandise ; 4 Case name & no Goods involved United Kingdom, 1 May 2012 The High Court of Justice, Queen's Bench Division [Commercial Court] (Kingspan Environmental Limited, Tyrrell Tanks Ltd, Rom Plastics Limitd, and Titan Enviornmental Ltd v. Borealis A/S and Borealis UK Ltd) Borecene (polymer used by claimants as the raw material with which to rotomould static tanks to hold bulk liquids) 2009 FOLIO 871 Spain, 16 February Margarine 2012 Las Palmas Canary Islands 70/2012 Delay between discovery of defect/ delivery of goods and notification of the defect Delivery between 23.01.02 to 25.10.02 (the 2 year period expired at various dates between 14 September 2003 and 16 September 2005) Holding (Reasonable or not) Five months The delay of notification was not reasonable. Failure to give notice within the time limits stipulated by Article 39 bars the buyer from pursuing any claim against the seller in respect of the alleged non conformity whether or not the buyer has then suffered loss thereby. The 2 year period, which begins on the date of delivery of the goods, is applied strictly. Subject always to Article 40, the buyer loses his right to rely on a lack of conformity, even in respect of a non-conformity which was not detected by the buyer after reasonable examination or one which was not capable of detection. If, therefore, the defect in question is a latent defect the buyer may have the whole of the 2 year period in which to give notice Notification was given but not beyond. Buyer contends that the defects in the present case were on 30 or 31 October latent defects such that it had until the expiry of the 2 year period in the 2002 by email and case of each delivery in which to give notice. during a meeting in (…) 19 January It is not apparent to (the judge) that notice of non-conformity should have 2005. been given at any time earlier than October 2002. Accordingly (the judge) do(es) not regard Buyer as time barred under Danish law in respect of RM 8402. The Court found that the goods had arrived in poor condition, the buyer having complained of defects five months after it had received them. In that connection, the Court held that, since margarine was undoubtedly a perishable product, the buyer had an obligation, under the Convention, to examine it as quickly as possible and, where appropriate, to complain of defects within a reasonable period of time. In the present case, the buyer 5 Case name & no Goods involved Delay between discovery Holding (Reasonable or not) of defect/ delivery of goods and notification of the defect had not undertaken such an examination nor lodged a complaint within a reasonable time, which should be measured in days or, at most, a number of weeks, but should never extend over a period of five months, which was the length of time that it had taken it to send a written communication clearly indicating the nature of the lack of conformity. Austria, 22 November 2012 Appellate Court Graz 3 R 192/12y A press Machine Austria, 14 February 2012 Supreme Court (Paprika case) 10 Ob 4/12d Paprika Powder The machine was delivered May-July 2006 and in October 2006 the press began to operate (from the beginning onwards it never worked properly). The notification of the defects was made in January/February/Marc h 2007 6 October 2003 delivery was of the powder was made; No control by the buyer; 3 December 2003 the authorities made a control; The court does not clarify whether the defect could have be detected already from the delivery or just from the “operating date”. Depending on this assessment the reasonable time period varies from 3 to 7 months The courts does not identify what would have been the time limit for the discovery of the defects, but it is of the opinion that more than 5 months between delivery and notification cannot been seen as reasonable time period for notifying the lack of conformity. 6 Case name & no Goods involved Delay between discovery of defect/ delivery of goods and notification of the defect 10 March 2004 - test result were notified; 16 March 2004 notification of lack of conformity Spain, 11 May 2012 Production machine The date from which the Court of First Instance for air conditioning time limit was of Fuenlabrada ducts calculated (dies a quo), 114/2012 as laid down in article 39 (2), had not even started, since there had been no formal recognition of the buyer’s taking possession of the machine and its accessories, in the form of documentation relating to occupational safety protection. France, 27 November Induction Cook tops Not specified 2012 Supreme Court Holding (Reasonable or not) In the case of non-perishable goods, or where a delay did not adversely affect the seller’s activities vis-à-vis third parties, the dies a quo of the “reasonable time” referred to in article 39 was the moment at which the buyer became certain, rather than merely suspecting, that the machine did not work (here he cited Saarbrücken Regional Court, 1 June 2004, and Forli District Court, 16 February 2009). The dies a quo should be different in the case of goods requiring a period of training and regular repairs (here he referred to the District Court for the Southern District of Ohio, United States of America, 26 March2009, and Versailles Court of Appeal, 29 January 1998). Court did not rule on reasonableness because buyer failed to prove the the different dates on which the goods were delivered. 11-14588 Mais attendu, en premier lieu, que dans ses conclusions d'appel, la société Rothelec invoquait l'expiration du délai de deux ans prévu par l'article 39.2 7 Case name & no Goods involved Delay between discovery Holding (Reasonable or not) of defect/ delivery of goods and notification of the defect de la CVIM, de sorte que la cour d'appel n'a ni méconnu les termes du litige ni violé le principe de la contradiction ; Attendu, en second lieu, qu'après avoir énoncé que le délai de l'article 39.2 de la CVIM court à compter de la date à laquelle les marchandises ont été effectivement remises à l'acheteur, ce qui suppose de connaître précisément la date de chaque vente Rothelec intervenue auprès de la société SMEG, notamment celle à laquelle la première a livré chaque table à induction, identifiable par son numéro de série, à la seconde, et qu'il n'est pas possible de se référer globalement aux livraisons au cours des années considérées, l'arrêt constate que la société SMEG, qui a la charge de prouver qu'elle a dénoncé le défaut de conformité dans le délai, omet de préciser et de justifier des différentes dates auxquelles elle a précisément obtenu livraison de chaque table litigieuse ; 2011 France 8 November Press Brakes 2011 Supreme Court 10-24691 The Fourth press brake was received the 28 September 2005 and put to work the 30 September 2005. Then there were problems, so the machine was stopped from 12 to 26 October 2005. The Court did not state whether such a delay of 14 months was reasonable or not but reprimanded the lower courts for not doing so. The Court also found that the Seller was within the 2 year period stipulated at article 40 of the CISG since the avoidance of the contract was based on the non-conformity of the goods. qu’en omettant de rechercher si l’assignation en résolution de la vente délivrée par la société GETEC à la société BYSTRONIC France par acte d’huissier du 28 décembre 2006, soit 14 mois après l’arrêt de la machine, 8 Case name & no Goods involved Italy 12 April 2011 Ceramic District Court Reggio Emilia N.505/2010 R.G Delay between discovery Holding (Reasonable or not) of defect/ delivery of goods and notification of the defect n’avait pas été délivrée dans un délai raisonnable au sens de l’article 49 de Seller moved the French la Convention de Vienne du 11 avril 1980, la Cour d’appel a privé sa décision courts to avoid the de base légale au regard du texte susvisé. contract by serving notice on 28 December Et alors, enfin, subsidiairement, qu’en tout état de cause selon l’article 39 2006 alinéa 2 de la Convention de Vienne du 11 avril 1980, l’acheteur est déchu du droit de se prévaloir d’un défaut de conformité s’il ne le dénonce pas au plus tard dans un délai de deux ans à compter de la date de la livraison ; que selon l’article 49 de la Convention, l’acheteur peut déclarer le contrat résolu en cas d’inexécution par le vendeur de l’une de ses obligations constituant une contravention essentielle au contrat ; qu’il est déchu du droit de déclarer le contrat résolu s’il ne l’a pas fait dans un délai raisonnable à partir du moment où il a eu connaissance ou aurait dû avoir connaissance de cette contravention ; qu’il en résulte que l’action en résolution de la vente, lorsqu’elle est fondée sur un défaut de conformité, peut être intentée dans un délai de deux ans à compter de la livraison ; qu’en retenant en l’espèce qu’en attendant 18 mois pour dénoncer sa demande de résolution concernant la 4ème plieuse, la société GETEC n’avait pas respecté un délai raisonnable, la cour d’appel a violé les textes susvisés. The ordered ceramic [Buyer] failed to comply with its obligation to inspect the goods pursuant material had been to Art. 38: this circumstance is evident from the fact that the products that delivered on 12 August 2003 and 9 September 9 Case name & no Goods involved Delay between discovery of defect/ delivery of goods and notification of the defect 2003 to [Buyer], which immediately (on the same dates) resold the goods to installer Henri Borner; [Buyer] received the complaint from Reinhold Seligmann, the final buyer of the goods, on 19 November 2003 and that the same party confirms that it has notified (verbally) the agent of [Seller] in Germany in the same month, November 2003 (in fact, the first written notification is dated 8 January 2004), two months after the last delivery; 2009 Netherlands , 11 February 2009, Trees Five working days Holding (Reasonable or not) had been bought from [Seller] were resold on the same day that they were delivered; -- considering that the aforementioned circumstance is decisive for the dies a quo of the "reasonable time" referred to in Art. 39 of the CISG: like already pointed out in several court decisions applying the CISG, the buyer (especially when a professional in the field, like [Buyer] in the present case) is requested to examine the delivered goods in a short time period to allow the seller to remedy its eventual non-performances (it was determined that in case the products are resold and the defect is discovered by a third party, the reasonable time period to examine the goods is 15 days), if the buyer fails to conduct the due examination, it loses its right to rely on the breach of the contract; With regard to the reasonable time period indicated in Art. 39 of the CISG the prevailing case law indicates that a period of one month (or a maximum of two months under specific conditions, that are not met in the present case) from the time when the buyer could (or could and should) have examined the goods can be considered adequate; The duration of this time period - five working days - is prima facie not unreasonable, as trees are living goods, that are sensitive to circumstantial 10 Case name & no Goods involved Rechtbank [District Court] Arhem Delay between discovery Holding (Reasonable or not) of defect/ delivery of goods and notification of the defect factors and depreciation, and given the fact that such a time period is also used by [Buyer] in its own general conditions. 172920 / HA ZA 08-1228 Netherlands, +& January 2009 Rechtbank [District Court] Breda Watermelons The Court thus agreed with the seller that the circumstances of the case demanded a very short notice period “… whereby [the buyer] should have complained either immediately, or at least a few days following delivery of the watermelons”. 197586 / KG ZA 08-659 Germany, 15 October 2009, District Court Stuttgart Printing machine Switzerland , 18 May 2009, Bundesgericht [Federal Supreme Court] Packaging machine Austria, 2 April 2009, Boiler Supreme Court Three months It is disputed how to measure the ‘reasonable time’ regarding the defect determined under Art. 39 CISG, however, according to jurisprudence and the leading doctrine, the gross average is approximately one month (cf. Schlechtriem/ Schwenzer, op. cit., No. 17, with further references). In any case, an almost three-month period between discovering and giving notice [of a defect], as is the case here, does not meet the requirements set out in Art. 39 (1) CISG"; In general, a period of one to two months will be necessary and reasonable for the buyer to sufficiently examine the situation, unless there is a special case which would objectively justify either an extended or a reduced period A period of fourteen days would be reasonable in order to examine the goods and give notice due to lack of special circumstances 11 Case name & no Goods involved Delay between discovery Holding (Reasonable or not) of defect/ delivery of goods and notification of the defect Germany, 2 April 2009, Automobile Appellate Court Hamm 2008 Germany, 19 May 2008, Appellate Court Köln Pesticides A notice of non-conformity must be sufficiently specific so as to enable the seller to form an idea about the defect and to take the necessary steps. A notice of non-conformity given six weeks after the discovery of the defect is not reasonable in the sense of Art. 39 CISG. Goods delivered February 2006 : The delay of 5 months was not reasonable. According to the court a “reasonable time” should have been a period of 14 days Notification of default: 28 "...this Court confirms the legal reasoning enunciated by the District Court July 2006 (denying a claim for damages on the part of [Buyer] on the grounds of a (Five months) 16 U 62/07 breach of duty to examine and notify under Arts. 38, 39 CISG). It is undisputed that the goods have been delivered in February 2006 and, according to [Seller's] submissions, complaints have been raised on 28 July 2006 for the first time. Switzerland, 18 August 2008, Obergericht [Appellate Court] Appenzell Ausserhoden Clothes In case the buyer passes goods on to his customers and if it is their customers who discover defects, then an examination period of two weeks and a notification period of four weeks is reasonable under the CISG"; 12 13