SPS 200 MHz RF Upgrade Highlights from 2013

Transcription

SPS 200 MHz RF Upgrade Highlights from 2013
SPS 200 MHz RF Upgrade
Highlights from 2013
Eric Montesinos
LIU-SPS coordination meeting 18 December 2013
SPS 200 MHz RF system upgrade
Highlights from 2013
Existing Amplifiers upgrade
tests above 1 MW peak in March
Upgrade ongoing
New RF Amplifiers
Drivers IT almost completed
Selected company under qualification
New RF Building
All authorizations obtained
IT completed, FC December, contract placed
LSS3 Tunnel integration
Cleaning cables campaign completed
HBWD integration started
18 December 2013
LIU SPS RF
2
SPS 200 MHz RF system upgrade
Highlights from 2013
Existing Amplifiers upgrade
tests above 1 MW peak in March
Upgrade ongoing
New RF Amplifiers
Drivers IT almost completed
Selected company under qualification
New RF Building
All authorizations obtained
IT completed, FC December, contract placed
LSS3 Tunnel integration
Cleaning cables campaign completed
HBWD integration started
18 December 2013
LIU SPS RF
3
SPS 200 MHz RF system upgrade
Highlights from 2013
Existing Amplifiers upgrade
tests above 1 MW peak in March
Upgrade ongoing
New RF Amplifiers
Drivers IT almost completed
Selected company under qualification
New RF Building
All authorizations obtained
IT completed, FC December, contract placed
LSS3 Tunnel integration
Cleaning cables campaign completed
HBWD integration started
18 December 2013
LIU SPS RF
4
SPS 200 MHz RF system upgrade
Highlights from 2013
Existing Amplifiers upgrade
tests above 1 MW peak in March
Upgrade ongoing
New RF Amplifiers
Drivers IT almost completed
Selected company under qualification
New RF Building
All authorizations obtained
IT completed, FC December, contract placed
LSS3 Tunnel integration
Cleaning cables campaign completed
HBWD integration started
18 December 2013
LIU SPS RF
5
SPS 200 MHz RF system upgrade
Highlights from 2013
Existing Amplifiers upgrade
tests above 1 MW peak in March
Upgrade ongoing
New RF Amplifiers
Drivers IT almost completed
Selected company under qualification
New RF Building
All authorizations obtained
IT completed, FC December, contract placed
LSS3 Tunnel integration
Cleaning cables campaign completed
HBWD integration started
18 December 2013
LIU SPS RF
6
Members
Dep-Group
Persons
BE-RF
Eric Montesinos, Charles Julie, SPS power team, Thomas Bohl, Wolfgang Höfle, Urs Wehrle, Elena
Shaposhnikova, Philippe Baudrenghien
BE-ABP
Ghislain Roy (BE space manager), Patrick Bestmann, Yannis Papaphilippou
BE-ASR
Marc Tavlet, Anne Funken
BE-BI
Christian Boccard, Patrick Odier
DGS-SEE
Guillaume Fontana, Cécile Pinto
DGS-RP
Nadine, Christophe
EN-CV
Mauro Nonis, Glen Mason, Aurelio Berjillos Barranco
EN-EL
Guillaume Gros, Jean-Pierre Sferruzza, Christophe Crombez, Denis Ribiollet
EN-HE
Caterina Bertone, Pascal Brunero, Serge Pelletier, Yann Seraphin, Patrick Vallet, Gilles Roche,
Helder Lorenco
EN-MEF
Frédéric Galleazzi, Yvon Muttoni, David McFarlane, Antoine Kosmicki, Emmanuel Paulat
GS-SE
Luz-Anastasia Lopez-Hernandez, Laurent Faisandel, Christophe Biot
TE-EPC
Gilles LeGodec, Christophe Coupat
TE-MSC
Jérémie Bauche
TE-VSC
Paolo Chiggiato, Antonio Mongelluzzo
18 December 2013
LIU SPS RF
7
THANK YOU FOR YOUR ATTENTION!