Fuel cell plant - a proposed analysis for economical feasibility of
Transcription
Fuel cell plant - a proposed analysis for economical feasibility of
FUEL CELL PLANT - A PROPOSED ANALYSIS FOR ECONOMICAL FEASIBILITY OF IMPLANTATION A . G . Amendola & M . C. Rocha Brazil SUMMARY The present paper has for objective to present a methodology to allow an accomplishment analysis of the economical feasibility of the implantation of a fuel cell plant . In the same way of the DSM actions and reduction of electric losses, the effect of the installation of a generation distributed in areas assisted by systems of Distribution is “seen " by the segments of the electric system located in a higher tension level of the installation point, as a load reduction. In other words, when another entity accesses the nets in the sense of generating a certain demand/energy, the whole system feels the influence of that access. In consequence, this installation postpones investments and expenses previously programmed in the expansion of these segments. The earnings of this postponement are the avoided costs, that are numerically same to the cost of supplying an additional unit of load in the point of the installation. As we walk along the electric system from the generation to the final consumers of low tension, these costs begin to grow, for the successive incorporation of new segments. A good measure to evaluate these avoided costs is the use of long term marginal costs, considered the same to the incremental medium costs of capacity and energy, that are calculated with base in the expansion plans (capacity) and operation (energy) of the systems located in a higher points . The economical feasibility of the distributed generation justifies itself when its cost goes smaller or equal at the cost avoided in the installation point, both yearly and expressed in R$/kW or R$/MWh. Although it has implicit character of located solution, which sends to the need of more detailed information, the distributed generation, approached in the present paper, adopted a medium consideration for the whole concession area, seeking, just, to provide an order of greatness of this viability. Of course, for the areas where the technicianoperational situation of the segments to amount goes more critical with the levels of service quality violated, certainly the distributed generation will be viable. The marginal costs of a load increment in these areas (equal at the avoided cost) they can have extremely high values, because the programs of expansion of these segments, besides they incorporate the service of the growth of the market, they will, also, consider the need of the recovery of service quality. It is where justified, priority, the installation of the distributed generation. The opposite will happen for the areas supplied through idle systems . For the effects of the calculations developed in this paper, it was limited, in beginning, that the installation happens in the low tension bus of the Distributing power stations. With that, they the costs of the expansion of the segments from the Distribution substations to the generation would be avoided (or moved), according to the Figure 1, below. PRODUCTION losses T TRANSMISSION los ses Power,Energy losses M edi um and Low Te ns ion Consum ption Figure 1 - Distributed Generation Of course, in theory, the distributed generation, can be installed in any point of the Distribution nets, as, for instance, in feeders. As mentioned, the more we walk towards the low tension consumers , the more this generation type is made possible, in terms of R$/kW or R$/MWh. However, is important to verify its technicaloperational feasibility. In this sense, it is proposed an analysis for distributed generation implantation, in a expedite way, considering the limits of actual values ( Investments + Fuel ) . At the end, the paper presents practical applications for important Brazilian utilities – CEEE and CEMIG . FUEL CELL USINE - UN PROPOSÉ ANALYSE POUR ÉCONOME FAISABILITÉ DE IMPLANTATION A . G . Amendola & M . C. Rocha Brèsil RESUMÉ Actuel article a pour objectif présenter une méthodologie qui permettre accomplissement analyse de économe faisabilité de implantation de fuel cell usine. Dans même chemin de DSM actions et réduction de électrique pertes, l´effet de installation de génération distribué dans régions aidai par systèmes de Distribution voit par segments de électrique système localisai dans haut tension aplanis de installation darde, as charge réduction. En des autres mots, quand another entité accès gagne dans sens de engendrant certain demande, ou énergie complet système sent influence de ce accès. In conséquence, ce installation ajourne investissements et dépenses précédemment programmed dans expansion de ces segments. earnings de ce ajournement évitent coûts, cette sommes numerically same à coûté de fournissant supplémentaire unité de charge dans point de installation. que nous marchons par électrique système de génération à final consommateurs de low tension, ces coûts commence grandir, pour successif incorporation de nouveau segments. bon mesure à évaluer ceux-ci évité coûts est usage de longtemps term marginal coûts, considéré même à incremental moyen coûts de capacité et énergie, cette calculons avec base dans expansion planifie (capacité) et opération (énergie) de systèmes localisé dans haut points. service de croissance de marché, ils aussi, considérerai besoin de récupération de service quality. Est où justifie, priorité, l´installation de le distribué génération. opposé passerai pour régions fournis through inactif systèmes. Pour effets de calculs développai dans ce article, il borna, dedans commençant, cette installation passe dans bas tension bus de Distribuant centrales. avec cette, ils coûts de expansion de segments de Distribution substations à génération éviterais (ou déplaçai,) selon Figure 1, au-dessous. PRODUCTION losses PERTES T TRANSMISSION Puissance, Enérgie los ses PERTES Power, Energy PERTES losses M edi um and Low Te ns ion Consommation des Clients Consum ption Moyenne et Bas Tension Figure 1 - Generation Distribué L´économe faisabilité de le distribué génération justifie quand son coût va petit ou paritaire à coût évité dans installation darder, both annuel et exprimai dans US$/kW et US$/MWh. Quoique il a implicite personnage de localisé solution, quels sends to besoin de détaillé information, le distribué génération, approcha dans actuel article, adopté moyen égard pour complet concession région, cherchant, justement, fournir commande de grandeur de ce viability. Naturellement, pour régions où technician-operational situation de segments à équivaloir va critique avec niveaux de service quality enfreignis, certainement le distribué génération sera viable. marginal coûts de charge increment dans ces régions (égalent à évité coût) ils ont extrêmement haut valeurs, because programmes de expansion de ces segments, de ailleurs ils incorporent Naturellement, dans théorie, le distribué génération, installe dans en point de Distribution filets, quant instance, dans feeders. aussi mentionnai, nombreux nous marchons pour bas tension consommateurs, nombreux ça génération caractère fait possible, en termes de US$/kW ou US$/MWh ou. cependant, est important vérifier sien technique faisabilité. Il est proposé un analyse pour l´implantation de la generation distribué dans une form vite em considerant les limits pour les actuells valeurs ( Investissements + nsidering the limits of actual values ( Investments + Fuel ) . À la fin, l´article présente pratique demandes pour important Brésilien concéssionaires – CEEE et CEMIG. FUEL CELL PLANT - A PROPOSED ANALYSIS FOR ECONOMICAL FEASIBILITY OF IMPLANTATION A . G . Amendola & M . C. Rocha Brazil ABSTRACT smaller or equal to the cost avoided in the installation point, both expressed in US$/kW or US$/MWh. When we settle a distributed generation in Distribution systems, the other segments above the “injection point” notice this installation as a load reduction, relieving all to the demand requested by this system. The implantation of the distributed generation justifies itself when its implantation cost goes smaller or equal at the cost avoided in the installation point, both expressed in US$/kW or US$/MWh. Such evaluation can be translated correctly with the aid of the long term marginal costs . Although the implicit character of a located solution, which sends to the need of more detailed information, the distributed generation, approached in the present paper, was addressed for a medium focus for the whole concession area, just seeking to provide an order of greatness of this feasibility. The present paper has for objective to present a methodology to allow to accomplish, in an expedite way, an analysis of the economical feasibility of the implantation of plants the cell of fuel. At the end, the paper presents practical applications for an important Brazilian utility . 1. PROPOSED METHODOLOGY 1.1. Conception of the Problem Of course, for the areas where the operational and technical situation of the segments above is more critical, with the levels of service quality violated, certainly the distributed generation will be viable. The marginal costs of a load increment in these areas (equal to the avoided cost) can have extremely high values, because the programs of expansion of these segments, besides incorporating the growth of the electric market, they should also consider the need of the recovery of the quality of service. It is where is justified in a priority way the use of distributed generation. The opposite will happen for the areas supplied through systems which operates with no load restrictions . For the effects of the calculations developed in this paper, it was limited, that the installation happens in the bus of low tension of the distributing substations, according to Figure 1, as follows. In the same way that the actions of DSM and reduction of electric losses, the effect of the installation of a distributed generation in areas assisted by distribution systems is noticed by the segments of the electric system, located above of the installation point, as A load reduction. In consequence, this installation postpones investments and expenses previously previewed in the expansion of those segments. The earnings of this postponement are the avoided costs, that are exactly the same of the cost of supplying an additional unit of load in the point of the installation. As we walk along the electric system, from the generation to the final low tension consumers, these costs grow, for the successive incorporation of new segments. A good measure to evaluate those avoided costs is the long term marginal costs, admitted the same of the medium incremental cost of capacity and energy, that are calculated with base in the expansion plans (capacity) and operation (energy) of the systems above. The economical feasibility of the distributed generation justifies itself when the cost goes PRODUCTION losses TRANSMISSION losses Power,Energy losses Medium and Low Tension Consumption Figure 1 - Distributed Generation With that, it would be avoided ( or “moved”) the costs of the expansion of the segments from the distributing substations to the generation, according to outline below. Of course, in theory, the distributed generation can be installed in any point of the distribution network, as, for instance, in specific feeders. As mentioned, the more we walk towards the low tension consumers, the more this generation type is made possible in terms of US$/kW or US$/MWh. however, it is important to verify its technical feasibility . the distributing substations, will be given by the following formula: CEVC = CMCG + CMT + CMSE (1) CEVE = CMEG (2) 1.2. Avoided Costs where: In this way, the generated power locally to supply part (or totally) of the growth of the maximum demand assisted by distributing power substations, will postpone investments to be done, not only, in the segments above, as well as, in own substation, (new enlargements and/or new substation). The earnings of this postponement are equal at the marginal cost of capacity (in US$/kW) until the point of installation of the plant, cost that is calculated with base in the marginal costs of each level and in the responsibility of the kW avoided in the Distribution on the maximum demands of the loads seen by each segment. For the evaluation of the impact of the reduction of the maximum demand at Distribution level in the costs of capacity of all of the segments above, it is necessary to verify the responsibility of this reduction is verified in the maximum demands of each segment and its participation in the power flow in each segment above. For that, it is necessary to know the load curves in distributing SE’s and in each one of the considered segments and the power flow between tension levels, that are established through load-flow studies. In the present paper, it was considered that the maximum demands were coincident, besides the one of the load avoided in the Distribution, because, in almost all of the segments, the period of the maximum demand is always dictated by the load of the Distribution. In located specific cases, however, they can happen diversities among the periods of those maximum demands. CEVC - avoided cost of capacity in US$/kW CEVE - avoided cost of energy in US$/MWh CMCG – generation marginal cost marginal of capacity, in R$/kW CMT - transmission marginal cost of capacity, in R$/kW CMSE – power substation marginal cost of capacity, in R$/kW CMEG – generation marginal cost marginal of energy, in R$/MWh To express CEVC and CEVE together through an annual value, it comes: CEV = CEVC x1000/(FC x 8760) + CEVE (3) where CEV is expressed in US$/MWh or: CEV´ = CEVE x FC x 8760 / 1000 + CEVC (4) where CEV´ is expressed in US$/kW 2. SOME RESULTS OBTAINED The responsibility for the establishment of the marginal cost of capacity of the kW avoided in the Distribution was determined only by the evaluation of the flows among tension levels. 2.1 Marginal Costs of the Distribution Suppliers Systems - CEEE The energy generated locally will avoid the production of energy for the plants of the segments above. So, without considering the efficiency improvement for the reduction of the losses (in power and energy) in the transmission systems of those segments, the avoided cost of energy will be the same of the marginal cost of energy of the suppliers systems and expressed in US$/MWh / year. For the transmission and, subtransmission and distribution networks, marginal costs of energy are not calculated. In that way, the annual cost avoided by the installation of a plant the cell of fuel in The calculations were developed (in preliminary estimation) for CEMIG and for CEEE (before the dismemberment). It was taken by base available information in ELETROBRÁS on the flows among tension levels, as established by the Marginal Costs Studies of Sub-Transmission and Transmission Networks, developed in 1999. In this paper we will show, in details, the results for CEEE For this utility, we still, assumed the medium marginal costs of the levels, for the South region . For CEMIG, we will show only the main results . For CEEE, the marginal costs in US$/kW-year used for the levels were the following ones: For the generation, the value of 40 R$/MWh was adopted, incorporating the marginal costs of capacity and energy. In this sense, considering this supply hypothesis, it results: A1(230 kV or higher) = 32 CEEE = 40 + 10,06 = 50 US$/MWh A2 (138 kV) = 48,3 A3 (69kV) = 28,35 For the level A1, we assume medium marginal costs for the SOUTH region . Figure 2 shows the flows in % for CEEE . CEEE If we imagine the additional supply for a gas thermal plant like Uruguaiana (30 US$/MWh), supplying the systems of those companies directly, without buying from Furnas and nor from Eletrosul , it comes: CEEE = 30 + 10,06 = 40 US$ /MWh MARGINAL COSTS IN UTILITY NETWORKS ITAIPU or ELETROSUL 27,5% ELETROSUL 29,7% 42,8% GENERATION A1 GENERATION 45,4% 72,4% 2,6% GENERATION 2.1.1 Distribution Power Stations. With base in the expansion programs for CEEE Distribution power substations, we calculated the long term medium incremental cost of capacity (LTIMC), in agreement with the formula: 25,0% 54,6% A2 A3 10,1% H ∑ t=1 75,8% Others ( 14,1%) Distribution Level A4+B I (t) (1+a)t LTIMC = (5) H ∆ M (t) ∑ t=1 (1+a) t Figure 2 - The Flows Among Levels For CEEE The main data, for CEEE, is shown in Figure 3, below: Considering the flows established among tension levels for the studies mentioned, we obtained the following values for the Distribution marginal costs of demand which passes through the segments of Transmission and Partition. For marginal cost in transmission networks ("seen" by Distribution) : CEEE INCR EM ENT AL M ÉDIUM COST ( Investiments Program Period : 8 y ears) y ear CMR’ = 0,101 * [48,3 + 0,454 * 32] + 0,758 * [28,35 + 0,724 * 32 + 0,25 * (48,3 + 0,454 * 32)] = 57,30 US$/kW.year Expressing in US$/MWh, it comes : CMR (US$/MWh) * FC*8760 = CMR’ (US$/kW-year) *1000 where FC (Charge Factor - year) ≅ 0,65 CMR = CMR’ * 1000/(FC * 8760) = 10,06 US$/MWh 0,55 0,1 Charge Factor A4 (55 %) Actualization Rate (10 %) A4’+B’ (GWh) 1997 1998 1999 2000 2001 2002 2003 2004 2005 4.412 4.706 4.954 5.214 5.465 5.770 6.080 6.401 6.734 y ears Inv est. 1998 1999 2000 2001 2002 2003 2004 2005 (R$) 8.434.190 10.253.150 6.617.600 600.000 1.200.000 1.400.000 2.300.000 1.500.000 Incr Energy (GW h) 0 293 248 260 250 306 309 322 332 Incr Deman d (GW) 0 0,060883354 0,051550436 0,054027812 0,051941469 0,063459112 0,064194479 0,066777709 0,06898983 Delta Energy (GW h) 293 248 260 250 306 309 322 332 Delta Deman d (GW) 0,060883354 0,051550436 0,054027812 0,051941469 0,063459112 0,064194479 0,066777709 0,06898983 VA1 VA2 (R$) 7.667.445 8.473.678 4.971.901 409.808 745.106 790.264 1.180.264 699.761 (GWh) 267 205 196 171 190 175 165 155 VA3 CIM LP (GW ) (R$/M Wh) 0,055348504 28,75 0,042603666 34,20 0,040591895 31,63 0,035476723 25,67 0,039403116 21,66 0,03623611 19,17 0,034267523 17,72 0,032184265 16,37 CIM LP (R$/kW) 138,53 164,79 152,39 123,68 104,34 92,36 85,37 78,89 10 yers period : CIMLP (R$/MW h) CIMLP (R$/kW ) 16,37 78,89 Value per year: Value per year: 2,46 11,83 US$/MW h US$/kW Figure 3 - Data For The For LTICM Calculation being obtained: CEEE = 79 US$/kW or 16,37 US$/MWh The differences between CEEE and CEMIG results are due the Ao level in CEMIG costs . In the formula above, I(t) and ∆M(t) are, respectively, the investment and the increment of the load (in kW and MWh) in the year t. H is the period of the expansion plan considered. This value in terms of US$/MWh comes : If we apply a factor = 15% (remuneration + depreciation + operation expenses and maintenance), it results, per year : CEMIG = 17,77 For generation, we adopted 40 US$/MWh, considering marginal costs of capacity and energy .. So : CEEE = 11,83 US$/kW or 2,45 US$/MWh CEMIG = 40 + 17,77 = 57,77 2.1.2 Costs in the Above Systems Due to the Additional kW Demanded by Distribution . In this sense, the marginal costs in US$/MWh of the above segments will be: Hypothesis I ≈ 58 US$/MWh Considering the supplying from Uruguaiana (30 US$/MWh), we will have : CEMIG = 30 + 17,77 ≈ 48 US$ /MWh Hypothesis II 2.2.1 Distribution Power Stations. With base in the expansion programs for CEMIG Distribution power substations, we calculated the long term medium incremental cost of capacity (LTIMC), according to formula (3) : CEEE = 2,45 + 40 ≈ 42,5 CEMIG = 200 US$/kW ou 41,6 US$/MWh CEEE = 2,45 + 50 ≈ 52,5 2.2 Main Results For CEMIG For CEMIG, the marginal costs in US$/kW-year used for the levels were the following ones : If we apply a factor = 15% (remuneration + depreciation + operation expenses and maintenance), it results, per year : CEMIG = 30,04 US$/kW or 6,23 US$/MWh Ao(Generation) = 51,0 A1(230 kV or higher) = 84,2 A2 (138 kV) = 41,7 2.2.2 Costs in the Above Systems Due to the Additional kW Demanded by Distribution . In this sense, the marginal costs in US$/MWh of the above segments will be: A3 (69kV) = 35,5 Hypothesis I For the A0 and A1 levels , we assumed values for SOUTHEAST/CENTER WEST region . Considering the flows among levels, we obtained the following value for marginal cost of demand :which passes through Transmission and Sub-Transmission networks : . CEMIG = 101,98 US$/kW-year CEMIG = 6,23+ 58 = 64,23 ≈ 64,2 Hypothesis II CEMIG = 6,23 + 48 = 54,23 ≅ 54,2 3. ESTIMATE OF COSTS TO THE FUEL CELL PLANTS M a r g in a l C o s ts T = 1 0 ye a r s T = 1 3 ye a r s T = 1 5 ye a r s H yp o th e s is I: 4 2 ,5 U S $ /M W h 875 US$ / kW 1 000 US$ / kW 1 075 US$ / kW H yp o th e s is II: 5 2 ,5 U S $ /M W h 1 075 US$ / Kw 1 250 U S$ / kW 1 325 US$ / kW CEEE The first evaluations on the costs of those plants resulted in values that can vary between 120 US$/kW and 1800 US$/ kW, with useful life between 10 and 15 years and already incorporating the costs per year of fuel, updated. Figure 5 – Final Results For CEEE Considering the updating tax of 10% and three hypotheses of useful life (10, 13 and 15 years), capacity factor equal 70% and load factor 55%, the values per year, in US$/MWh (tariffs) are presented in the Graph 1, below, as a function of plants costs mentioned in the previous paragraph. Cost of Energy per Year (US$ / MWh-year) 100,0 Just as general reference, if we consider a 15 year-old useful life for the plants and marginal costs of the systems (from generation to Distribution power substations) near 43 US$/MWh - year, the feasibility will be proven for cost of the investment of the plant (added of the updated values of the annual costs of fuel) up to 1100 US$/kW. As, in practice, the appeal to the use of local generation will be larger in areas with supplying problems and, for that, with larger marginal costs, the feasibility will be guaranteed even for values above 1100 USS/kW. 80,0 60,0 40,0 20,0 0,0 0 500 1000 1500 2000 Investiments + Fuel (US$ / kW) Graph 1 - Tariffs For 3 Hypothesis of Useful Life as a Function of Costs per Year 4. CONCLUSIONS Taking into account the results of the above items, and considering the hypotheses of the several useful lives, the plants to cells of fuel are made possible for CEMIG and CEEE if the current values of their costs are, at the maximum, the same of the ones, according to Figures 4 and 5, below : M a r g in a l C osts T = 1 0 y ea r s T = 1 3 ye a r s T = 1 5 ye a r s H yp oth e sis I: 5 4 ,2 U S $ /M W h 1 100 US$ / kW 1 300 R$ / kW 1 375 US$ / kW H yp o th e sis II : 6 4 ,2 U S $ /M W h 1 325 US$ / kW 1 525 R$ /k W 1 625 US$ / kW If we admit, for hypothesis, a value limits of 65 US$/MWh -year for the marginal costs of the systems, the value to the plant would be of 1650 US$/kW, for 15 years of useful life. Although the process described is specific for 2 important Brazilian utilities , like CEEE and CEMIG, with the values presented above, it is possible to generalise the same method for any others cases . In this sense, we proposed a feasibility analysis for distributed generation implantation, in a expedite way, considering the limits of actual values ( Investments + Fuel ) . It is convenient to reaffirm that the present paper proposes an economics analysis for distributed generation implantation, without considering operational feasibility aspects, like power stations loads, tension drop, limits of demands, and so on . REFERENCES C E M IG 1. Amendola, A.G., 1992, "Distribution Marginal Costs", Eletrobrás, Brazil This work is in the Public Domain Figure 4 – Final Results For CEMIG