PRESS RELEASE
July 29th 2010
CWE/Nordic coupling joint target launch date
On 7 of May 2010, in Bonn and in presence of the CWE-Nordic Regulators, the
CWE-Nordic TSOs, Power Exchanges and EMCC committed to prepare for a
simultaneous go-live (launch) of the CWE-Nordic Interim Tight Volume Coupling
(ITVC) solution and the CWE Price Coupling solution, as close as possible to 7 of
September 2010, the initial target launch date for the CWE region.
The ITVC solution is based on the existing EMCC tight volume coupling model on the
German borders with Denmark and Sweden. It is scheduled to be implemented in
two steps, with the NorNed cable being integrated in the second step. The ITVC is an
interim solution that will be replaced by an enduring price coupling solution covering
at least the entire CWE and Nordic regions. The CWE and Nordic parties have
established a detailed project planning, including alignment of business processes
and testing of the solution according to the necessary quality standards. The
planning also caters for testing of the operational fall back mechanism, i.e. shadow
auctions performed by CASC-CWE which is planned to be in place from the start of
ITVC.
According to this planning, the combined target launch date of the ITVC step 1
solution and CWE Price coupling is 9 November 2010. The target launch date of
ITVC step 2, including NorNed capacity, is 14 December. Both target launch dates
are subject to successful completion of all necessary tests and subject to regulatory
approval of the solution. Confirmation of a firm launch date for step 1 is expected to
be given by mid September.
CWE, EMCC and Nordic parties
Press contacts
Company
Contact
Telephone & e-mail
50Hertz Transmission
GmbH
Jens Mattausch
+49 30 5150 4583
[email protected]
Volker Kamm
+49 30 5150 3417
[email protected]
Marian Rappl
+49 231 438 3679
[email protected]
APX-ENDEX
Sanna-Maaria Mattila
+31 20 305 4000
[email protected]
Belpex
Rob Loos
+32 2 546 70 57
[email protected]
Creos
Danielle Schmit
+352 26 24 80 77
[email protected]
Elia
Eva Suls
+32 477 48 80 09
[email protected]
Lise Mulpas
+32 478 65 28 90
[email protected]
EMCC
Vivien Neubert
+49 40 36 90 54 60
[email protected]
EnBW
Transportnetze
Kirsten Koenigs
+49 711 128-2271
[email protected]
Energinet.dk
Lene Sonne
+45 23 33 88 02
[email protected]
EPEX Spot
Wolfram Vogel
+33 1 73 03 61 32
[email protected]
Nord Pool Spot
Siw Hauge
+47 67 10 91 00
[email protected]
RTE
Alexia Rière
+ 331 41 02 15 69
[email protected]
Statnett SF
Kjell A Barmsnes
+47 23 90 30 00
[email protected]
Svenska Kraftnät
Maria Jäderberg
+46 8 475 8010
[email protected]
TenneT
Jelle Wils
+31 26 373 13 75
[email protected]
Transpower
Stromübertragungs
gmbh
Joëlle Bouillon
+49 921 915 4046
[email protected]
[email protected]
Amprion
2
COMMUNIQUÉ DE PRESSE
29 Juillet 2010
Date cible de lancement conjoint des couplages CWE – Nordique
Le 7 mai 2010 à Bonn, en présence des régulateurs des régions CWE (Central West
Europe ) et Nordique (Scandinavie), les GRT et les bourses de ces mêmes régions ainsi
qu’EMCC se sont engagés comme suit : le couplage temporaire par les volumes appelé
ITVC (Interim Tight Volume Coupling) entre la région nordique et CWE et le couplage par les
prix (Price coupling) au sein de la région CWE seront lancés simultanément à une date aussi
proche que possible du 07 septembre 2010, date cible initiale de lancement du couplage
CWE.
La solution ITVC est basée sur le modèle de couplage par les volumes actuellement opéré
par EMCC sur les frontières allemandes avec le Danemark et la Suède. Son implémentation
est prévue en 2 étapes, la liaison « NorNed » (câble Norvège – Pays bas) étant intégrée lors
de la deuxième étape. L’ITVC est une solution temporaire qui sera remplacée à terme par
une solution pérenne de couplage par les prix couvrant a minima les zones CWE et
Nordique. Les partenaires CWE et Nordique ont mis au point un échéancier de projet
détaillé, incluant l’harmonisation des processus opérationnels respectifs de même qu’une
phase de tests conforme aux normes de qualité requises. Le planning tient également
compte des tests de mode dégradés, i.e. des enchères explicites appelées « shadow
auctions » opérées par CASC – CWE, qui seront mises en place dès le lancement de l’ITVC.
Conformément à cet échéancier, la date cible de lancement simultané de l’étape 1 de l’ITVC
et du price coupling CWE est le 09 novembre 2010. La date cible du lancement de l’étape 2
de l’ITVC, intégrant NorNed est le 14 décembre 2010. Ces deux échéances sont
conditionnées par la réussite de tous les tests requis d’une part, et par l’approbation des
régulateurs d’autre part. La confirmation de la date ferme de lancement de l’étape 1 de
l’ITVC est attendue à la mi-septembre.
Les partenaires CWE, EMCC et Nordiques
3
Contacts Presse
Société
Contact
Téléphone & e-mail
50Hertz Transmission
GmbH
Jens Mattausch
+49 30 5150 4583
[email protected]
Volker Kamm
+49 30 5150 3417
[email protected]
Marian Rappl
+49 231 438 3679
[email protected]
APX-ENDEX
Sanna-Maaria Mattila
+31 20 305 4000
[email protected]
Belpex
Rob Loos
+32 2 546 70 57
[email protected]
Creos
Danielle Schmit
+352 26 24 80 77
[email protected]
Elia
Eva Suls
+32 477 48 80 09
[email protected]
Lise Mulpas
+32 478 65 28 90
[email protected]
EMCC
Vivien Neubert
+49 40 36 90 54 60
[email protected]
EnBW
Transportnetze
Kirsten Koenigs
+49 711 128-2271
[email protected]
Energinet.dk
Lene Sonne
+45 23 33 88 02
[email protected]
EPEX Spot
Wolfram Vogel
+33 1 73 03 61 32
[email protected]
Nord Pool Spot
Siw Hauge
+47 67 10 91 00
[email protected]
RTE
Alexia Rière
+ 331 41 02 15 69
[email protected]
Statnett SF
Kjell A Barmsnes
+47 23 90 30 00
[email protected]
Svenska Kraftnät
Maria Jäderberg
+46 8 475 8010
[email protected]
TenneT
Jelle Wils
Transpower
Stromübertragungs
gmbh
Joëlle Bouillon
Amprion
+31 26 373 13 75
[email protected]
+49 921 915 4046
[email protected]
[email protected]
4
PRESSEMITTEILUNG
29. Juli 2010
Gemeinsamer Starttermin für CWE/Nordic Market Coupling
Am 7. Mai 2010 wurde zwischen den Übertragungsnetzbetreibern und den
Strombörsen der Regionen „Central Western Europe“ (CWE) und „Nordic“ sowie der
„European Market Coupling Company“ (EMCC) in Bonn unter Beisein der CWE- und
Nordic- Regulatoren Folgendes vereinbart: Die Kopplung beider Regionen über das
„Interim Tight Volume Coupling“ (ITVC) sowie die Preiskopplung innerhalb der CWE
Region („CWE Market Coupling“) sollen gleichzeitig und möglichst zeitnah zum 7.
September 2010, dem ursprünglich geplanten Starttermin für das CWE Market
Coupling, gestartet werden.
Das ITVC basiert auf dem bereits an der schwedisch-dänisch-deutschen Grenze
existierenden “Tight Volume Coupling“-Modell. Die Implementierung des ITVC ist in
zwei Schritten geplant, wobei das NorNed Seekabel erst im zweiten Schritt integriert
werden soll. Dabei stellt das ITVC lediglich eine Zwischenlösung dar und wird durch
eine dauerhafte Preiskopplung ersetzt werden, die zumindest die gesamte CWE- und
Nordic-Region abdeckt.
Seitens der CWE-/Nordic-Parteien wurde ein detaillierter Projektablaufplan
entwickelt, der u.a. die Aufstellung der Geschäftsprozesse sowie Tests des
Verfahrens gemäß der geforderten Qualitätsstandards umfasst. In diesem Rahmen
sind darüber hinaus Tests der operativen Rückfallebene vorgesehen, d.h. der seitens
CASC-CWE durchgeführten Schattenauktionen, die von Beginn an verfügbar sein
sollen.
Gemäß dieser Planung ist als gemeinsamer Starttermin für den ersten Schritt des
gemeinsamen Verfahrens aus ITVC und CWE Market Coupling der 9. November
2010 vorgesehen. Als Starttermin für den zweiten Schritt des Verfahrens unter
Einbeziehung der Kapazität des NorNed Seekabels ist der 14. Dezember geplant.
Voraussetzungen für beide geplanten Starttermine sind der erfolgreiche Abschluss
aller notwendigen Tests und die regulatorische Zustimmung zu den Verfahren. Die
Bekanntgabe eines endgültigen Starttermins wird Mitte September erwartet.
Die CWE, EMCC und Nordic Partner
5
Pressekontakte
Gesellschaft
Kontakt
Telefon & E-mail
50Hertz Transmission
GmbH
Jens Mattausch
+49 30 5150 4583
[email protected]
Volker Kamm
+49 30 5150 3417
[email protected]
Marian Rappl
+49 231 438 3679
[email protected]
APX-ENDEX
Sanna-Maaria Mattila
+31 20 305 4000
[email protected]
Belpex
Rob Loos
+32 2 546 70 57
[email protected]
Creos
Danielle Schmit
+352 26 24 80 77
[email protected]
Elia
Eva Suls
+32 477 48 80 09
[email protected]
Lise Mulpas
+32 478 65 28 90
[email protected]
EMCC
Vivien Neubert
+49 40 36 90 54 60
[email protected]
EnBW
Transportnetze
Kirsten Koenigs
+49 711 128-2271
[email protected]
Energinet.dk
Lene Sonne
+45 23 33 88 02
[email protected]
EPEX Spot
Wolfram Vogel
+33 1 73 03 61 32
[email protected]
Nord Pool Spot
Siw Hauge
+47 67 10 91 00
[email protected]
RTE
Alexia Rière
+ 331 41 02 15 69
[email protected]
Statnett SF
Kjell A Barmsnes
+47 23 90 30 00
[email protected]
Svenska Kraftnät
Maria Jäderberg
+46 8 475 8010
[email protected]
TenneT
Transpower
Stromübertragungs
gmbh
Jelle Wils
Amprion
Joëlle Bouillon
+31 26 373 13 75
[email protected]
+49 921 915 4046
[email protected]
[email protected]
6